How is a wind turbine built?

Discover in the video, the exciting structure of a wind turbine.

;;

As soon as all permits have been granted and contractual processes have been completed, it will get exciting: Within the next 15 months, all parts needed for the construction of a wind turbine will be delivered. In the meantime, we can already create all the important prerequisites for the installation, including necessary ground improvements, preparing the pit, as well as constructing the foundation and electrical lines or setting up a substation. After the actual construction, the manufacturer of the wind turbine checks the proper installation of all components, with the final acceptance carried out by the TÜV. By the way, the construction of the wind turbine depends on its height: for turbines over 125 meters hub height, a hybrid system of concrete and steel elements is often preferred, while smaller turbines are usually entirely made of steel.


Step 1

Applications, discussions and approvals

Before the actual construction of a wind turbine can begin, extensive organisational preparations and the completion of all necessary approval procedures are required.


Step 2

The way to the goal: building access roads

The second step in the construction of a wind turbine involves creating the necessary infrastructure, in particular the access routes to the construction site and the wind turbines.


Step 3

Foundation construction: The basis of the wind turbine

Now the excavation pit for the foundation is dug, the depth and nature of which vary depending on the location and geological conditions.


Step 4

Ecological responsibility: consider species protection and compensatory measures

Species protection and corresponding compensation and replacement measures play a decisive role in the construction of a wind turbine.


Step 5

Assembling the wind turbine: precise assembly

As soon as the contract is valid and the delivery times for the components are finalised, we start with the detailed scheduling. This involves pre-calculating all the phases, such as the construction of the foundations and the laying of the cables.


Step 6

Construction successful: the plant is up and running

As soon as the installation of the wind turbine has been completed, it is commissioned by the manufacturer.


Step 7

Start of operation: Green energy for the region

As soon as the wind turbine has been successfully commissioned, a new test phase begins. During this time, the turbine is intensively monitored to ensure that it runs smoothly and fulfils the specified performance standards.

Questions and Answers about the Construction of a Wind Turbine

For a Greener Future

Project development
Our projects
Construction diary wind farm Oldendorf

Social media





Language (Country)


Prokon eG 2024. All rights reserved.